Guadalupe and Lowry Streets Reconstruction
Project Information
-
Engineer's estimate: $1,299,896.58
-
Funded by: 2002 Series Bond Project
-
Bid awarded to: MPB, Inc., Kerrville, TX (view this project's bid log and bidders list)
-
Project start date: July 28, 2003
-
Project status:
-
100% Complete (June 2004)
-
99% Complete (May 2004)
-
90% Complete (April 2004)
-
77% Complete (March 2004)
-
61% Complete (February 2004)
-
59% Complete (January 2004)
-
50% Complete (December 2003)
-
39% Complete (November 2003)
-
27% Complete (October 2003)
-
18% Complete (September 2003)
-
7% Complete (August 2003)
-
Project end date: June 8, 2004
Plans & Documents
To view the files below you must have the free Adobe Acrobat Reader installed on your computer.
- Addendums
-
Addendum One: Moved date of bid opening to June 11, plans available at
Kerrville
-
Addendum Two: Delete bid item two and clarification of rock rip rap
gabion
- Aerial Views
-
2003 aerial photo of project (11/25/2003)
-
Aerial view of project
- Construction schedule information
-
Construction Schedule
-
Construction Schedule Map
|
- Geotech Report: Does not include the logs, but table on page
three
shows typical depths of material encountered
- Plans and Specs
-
Guadalupe and Lowry Streets Reconstruction Plans: Non-Bidding, Sheet
Three purposely removed from document to keep file size small.
-
Guadalupe and Lowry Streets Reconstruction Specs
-
Project Sign
-
Traffic Counts
|
|
|