Guadalupe and Lowry Streets Reconstruction
Project Information
  • Engineer's estimate: $1,299,896.58
  • Funded by: 2002 Series Bond Project
  • Bid awarded to: MPB, Inc., Kerrville, TX (view this project's bid log and bidders list)
  • Project start date: July 28, 2003
  • Project status:
    • 100% Complete (June 2004)
    • 99% Complete (May 2004)
    • 90% Complete (April 2004)
    • 77% Complete (March 2004)
    • 61% Complete (February 2004)
    • 59% Complete (January 2004)
    • 50% Complete (December 2003)
    • 39% Complete (November 2003)
    • 27% Complete (October 2003)
    • 18% Complete (September 2003)
    • 7% Complete (August 2003)
  • Project end date: June 8, 2004

Plans & Documents
To view the files below you must have the free Adobe Acrobat Reader installed on your computer.
  • Addendums
    • Addendum One: Moved date of bid opening to June 11, plans available at Kerrville
    • Addendum Two: Delete bid item two and clarification of rock rip rap gabion
  • Aerial Views
    • 2003 aerial photo of project (11/25/2003)
    • Aerial view of project
  • Construction schedule information
    • Construction Schedule
    • Construction Schedule Map
  • Geotech Report: Does not include the logs, but table on page three shows typical depths of material encountered
  • Plans and Specs
    • Guadalupe and Lowry Streets Reconstruction Plans: Non-Bidding, Sheet Three purposely removed from document to keep file size small.
    • Guadalupe and Lowry Streets Reconstruction Specs
  • Project Sign
  • Traffic Counts